Procurement

This material is based upon work supported by the U.S. Department of Energy’s Grid Deployment Office, Award Number DE-GD0000885.

Consortium Member Information

Since 1938, Ravalli Electric Cooperative has been dedicated to providing safe, reliable, and affordable power to our valued membership. Serving over 12,000 meters and more than 9,400 members, we proudly support the communities of Ravalli County. As a member-owned cooperative, we are committed to delivering exceptional service and powering the lives of our neighbors every day. REC’s peak demand is 55MW, with 1355 miles of distribution lines and 36 employees.

Ravalli Electric Cooperatrive Inc. is a member of a consortium of 35 electric co-ops selected to receive federal funding through the Wildfire Assessment and Resilience for Networks project, or “WARN.” Led by Holy Cross Energy in coordination with NRECA Research, WARN will provide more than $145 million in wildfire mitigation funding to co-ops across 17 states in the central and western United States to drive energy resilience in high-risk rural areas.

Project Description     

Ravalli Electric Cooperative has proposed to replace overhead powerlines in the West Fork of the Bitterroot River in the southern end of Ravalli County. The project area falls within a high wildfire risk area. There are residential homes, U.S. Forest Service buildings, critical communication towers, hiking trails and other outdoor activities in the area.

REC has also proposed replacing antiquated oil filled reclosers with electronic reclosers and controls with advanced modeling, communications, and adaptive protection technologies. This will allow the system to be more resilient, creating less outages and shorter duration of outages. The use of these methods and devices will allow SCADA control which will significantly help with fire mitigation measures. The replacement of expulsion fuses with new vacuum technologies will also be implemented.

The estimated project cost for labor and materials is $5.8 million. 

Benefits

Burying power lines offers numerous benefits, making it a smart and forward-thinking investment. Underground lines are significantly safer, as they eliminate the risk of falling wires during storms, accidents, or other disruptions. While the initial cost may be higher, underground systems are more affordable in the long run due to reduced maintenance, fewer outages, and lower repair costs. Additionally, buried lines help mitigate wildfire risks by removing overhead wires that can spark fires in dry, windy conditions. This approach also hardens the system, making it more resilient to natural disasters and ensuring a more reliable power supply for the community.

Community and Consumers Impacted

The East & West Fork River corridors in the rural southern section of the Bitterroot Valley are home to blue ribbon trout fishing, countless hiking trails and access to public lands. It is also home to almost 1,700 member meters, the majority falling within the WUI. The overhead to underground conversion will take place from MM 14.35 to MM 21 along the West Fork Rd. All overhead powerlines in this section will be converted to underground. The rest of the West Fork, East Fork and Tin Cup areas will benefit from new electronic vacuum recloser and fuse replacement.

Ravalli Electric currently serves power to 1691 members in the project area. The accounts mostly consist of residential homes. However, there are several volunteer fire depts, EMS services, communication towers, gas stations, convenience stores and restaurants throughout the territory.

Timeline

This project is expected to take place over 5 years. Construction will be broken down into four stages with each stage consuming an entire construction season. The construction seasons in the project area will start at approximately the beginning of May and will conclude at the end of October each year.

  • Design: 8 months
  • Permitting: Overhead easements will be replaced with underground easements.
  • Construction: May – October, 2026-2029. 7 miles of this project will be constructed along an existing road. There will be some level of traffic control in certain areas. The construction equipment will consist of backhoes, excavators and boring equipment.
  • Other: Converting overhead to underground will include building out a new underground feeder. Construction crews will then convert the existing overhead services to underground. Once this work is completed all overhead lines will be retired.
  • Operation: Expected completion of underground infrastructure and energization – Fall 2029

Procurement

For the General Materials RFP, Recloser & Pad Mount Switchgear RFP and the Primary Cable RFP, REC seeks competitive bids for the supply of equipment and materials required to build out the REC – WARN Project. All materials purchased under this RFP must comply with the Build America, Buy America Act (BABA). Please click the applicable link below for more details, and to request an RFP.

General Materials Information Recloser & Pad Mount Switchgear Information Primary Cable Information

 

Responses to Clarification Questions

Grid Upgrade Plan

Grid Upgrade Plan

 

Contact for More Information

Additional questions should be directed to:

Joe Parsons, Project Manager

406-642-8712

rfp@ravallielectric.com